Project management and reporting

Contents

Subcontracting rules

Subcontracting means that certain project tasks (“(action) tasks”) defined in Annex 1 of the Grant Agreement (GA) are outsourced by project partners to external third parties (i.e. subcontractors) if these tasks are not or cannot be carried out by the beneficiaries themselves.

A subcontractor is contracted by a beneficiary to implement a specific (action) task, delivers the agreed service (e.g. works, services or goods), invoices the beneficiary, and is paid a market price.

Costs for subcontracting are not included in the calculation of the 25% flat rate for indirect costs.

Eligibility criteria

For subcontracting costs to be eligible, the following conditions must be fulfilled:

  • The outsourced tasks are clearly described as “(action) tasks” in Annex 1 of the GA.
  • The corresponding costs are foreseen in the budget (Annex 2 of the GA, category B (PDF).).
  • The award of the subcontract complies with the principles of:
    • transparency,
    • equal treatment, and
    • best value for money (or lowest price, where appropriate).
    • No conflict of interest exists.

The inclusion of a subcontractor after the start of the project is possible:

  • either through an amendment to the GA, or
  • through a simplified approval procedure (in this case, the beneficiary bears the risk of ex-post approval by the European Commission).

Liabilities and obligations

Beneficiaries remain fully liable towards the European Commission, both:

  • technically (e.g. proper implementation of the action task), and
  • financially.

They must ensure that subcontractors comply with relevant obligations under the GA (e.g. audit rights of the European Commission).

Limitations

Subcontracting is not allowed in the following cases:

  • Subcontracting to other beneficiaries within the same project
  • Outsourcing of core project tasks (in particular tasks of the coordinator)
  • Subcontracting is only allowed in duly justified exceptional cases for:
  • Subcontracting to affiliated entities

How subcontracting (category B) and purchases (category C) differ

  • Purpose: subcontracting covers action tasks set out in Annex 1 of the grant agreement. Purchases support beneficiaries in carrying out those tasks.
  • Description in the grant agreement: subcontracting must be described in Annex 1. Purchases do not need to be described there.
  • Indirect costs: subcontracting costs are excluded from the calculation of the 25% flat rate for indirect costs. Purchase costs are included.

Further Information: AGA, Articles 6.2.B and 9.3 (PDF)